3 offshore projects at Isumi City offshore, Chiba Pref.
3 Document on Primary EIC
3 Document on Primary EIC
Isumi City offshore windfarm project
Project area Chiba Pref. Isumi City offshore
Developers Chiba Offshore Wind KK
Capacity 500,000kW
Schedule Construction 40-50 months
Commercial production 51month
Isumi City offshore windfarm project
Project area Chiba Pref. Isumi City offshore
Developers Green Power Investment Corporation
Capacity 630,000kW
Schedule Construction start at 2029autumn
Commercial production 2032autumn
Aomori Pref. Tsugaru city・Ajigasawa town offshore windfarm project
Project area Aomori Pref. Tsugaru city, Nishi-Tsugaru county Ajigasawa town
Developers TOKYU LAND CORPORATION・CI IV Transfer Coöperatief U.A.
Capacity 600,000kW
Schedule construction about 3years
Aomori offshore windfarm project
Project area Aomori Pref. Tsugaru city, Ajigasawa town
Developers Tsugaru-shichirinagahama offshore windfarm GK(Japan Windenergy KK)
Capacity 600,000kW
Schedule construction 3years, commercial production late 3rd year
Shimamaki village offshore windfarm project
Project area Hokkaido Shimamaki village offshore
Developers HOKKAIDO OFFSHORE WIND DEVELOPMENT GK
Capacity 585,000kW
Construction 24 months
8 Document on Primary EIC
Ishikari Bay offshore windfarm
Project area Hokkaido Ishikari City, Otaru city offshore
Developers Japan Wind Development Co., Ltd.
Capacity 3,000,000kW
Commercial Production 2030
Niigata Pref. Murakami City ・Tainai city (Japan Sea) offshore windfarm project
Project area Niigata Pref. Murakami City ・Tainai city offshore
Developers Invenergy wind G.K.
Capacity 450,000kW
Chiba Pref. Isumi City offshore windfarm project
Project area Chiba Pref. Isumi City offshore
Developers RENOVA, Inc.
Capacity 450,000kW