Recommendation from Minister of METI Nov.1
Construction machine
Avoid and reduce influence to Living environment
=Take environmental protection measures, if necessary
Bat
Conduct post-survey for batstrike
=If a significant impact has been confirmed, take the appropriate environmental protection measures
Project Area
Akita Pref. Noshiro Port renewable energy area
Developers
Akita offshore Windfarm Corporation
Capacity
88,200kW、21×4.2MWturbines
Development status
Env. assessment Draft EIS: Recommendation from Min.METI Nov.1 ,2018
Construction Oct. 2019 〜 Mar. 2021
Commercial Production Apr. 2021
Construction Schedule from Draft EIS
Onshore Oct. 2019 〜 Oct. 2020
Offshore Mar. 2020 〜 Oct. 2020
Commissioning Nov. 2020 〜 Mar. 2021
Commercial Production Apr. 2021