Project area
Akita Pref. Noshiro City, Mitane Town, Oga City offshore
Developers
Mitsubishi Corporation Energy Solutions Ltd. 、C-TECH CORPORATION、Mitsubishi Corporation
Capacity
532,000kW 12,600~14,000kW×38turbines
Development status
Env. assessment 2022, Jun. Scoping document
Schedule Construction Jun.2027
Commercial production Dec.2028