Oga city, Katagami city and Akita city offshore windfarm project: Scoping Document open for public from Jul. 28
Oga city, Katagami city and Akita city offshore windfarm project
Project area Akita pref. Oga city, Katagami city and Akita city offshore. Promotion Zones for the Development of Marine Renewable Energy Power Generation Facilities
Developers JERA Co., Inc.、Electric Power Development Co.,Ltd.、ITOCHU Corporation、Tohoku Electric Power Co.,Inc.
Capacity 315,000kW
Construction start : under consideration
Commercial production : 24months after construction start
Wakayama Pref. offshore project: Document on Primary EIC open for public from Jul.4
Wakayama Pref. offshore project
Project area Wakayama Pref. Mihama town, Shirahama town offshore
Developers The Kansai Electric Power Company,Incorporated、RWE Renewables Japan G.K.
Capacity 1,000,000kW
Schedule Currently under consideration
8 offshore projects at Murakami City and Tainai City offshore, Niigata Pref.
5Scoping Document 3Document on Primary EIC
Tokushima Pref. Minami town offshore project: Document on Primary EIC open for public from Jun. 16
Tokushima Pref. Minami town offshore project
Project area Tokushima Pref. Kaifu county, Minami town offshore
Developers SSE Pacifico K.K.
Capacity 420,000kW
Schedule To be considered in the future
Niigata Pref. Murakami city and Tainai city offshore project: Document on Primary EIC open for public from May 22
Niigata Pref. Murakami city and Tainai city offshore project
Promotion Zones for the Development of Marine Renewable Energy Power Generation Facilities
Project area Niigata Pref. Murakami city, Tainai city offshore
Developers SSE Pacifico K.K.
Capacity 420,000kW
Schedule Currently under consideration
Niigata Pref. Murakami City ・Tainai city (Japan Sea) offshore windfarm project : Scoping Document open for public from May16
Niigata Pref. Murakami City ・Tainai city (Japan Sea) offshore windfarm project
Project area Niigata Pref. Murakami City ・Tainai city offshore
Developers Invenergy wind LLC
Capacity 700,000kW
Schedule Construction 1st year~3rd year
Commercial production 3rd year